50 MWp wind power plant feasibility study. Wind potential analysis, site selection and techno-economic feasibility report preparation in Izmir region.
Goal
50 MWp wind power plant feasibility study. Wind potential analysis, site selection and techno-economic feasibility report preparation in Izmir region.
Solution
Following detailed roof analysis and feasibility study, turnkey EPC project was implemented.
Technical Details
Turbine Model: Vestas V150-5.6 MW (9 units)
Tower Height: 105 meters hub height
Rotor Diameter: 150 meters
Wind Measurement: 12-month met mast data analysis
Grid Connection: 154 kV substation connection
Site Analysis: Topography, geology and environmental impact assessment
Power
50,00 MWp
Annual Production
140,00 GWh
CO₂ Reduction
65.000 ton
Energy Savings
0,00%